A38 project timeline

We secured Department for Transport funding to develop the full business case in autumn 2023. Proposals for each of the nine locations are now being designed and developed. 

In June 2025, we appointed Octavius who will help deliver the works. Their first task will be the completion of a detailed design. This will allow us to submit a full business case to the Department for Transport.

The business case must be approved before any construction can begin.

Current timeline

Anticipated dateActivity
Early 2026Cabinet approval to submit full business case
Early 2026Submission of full business case to Department for Transport, review period to confirm construction funding award and associated governance
Spring 2026North Somerset Council acceptance of funding and update to capital programme (dependent on Department for Transport response times)
Spring 2026 Award of Stage 2 Design & Build and Professional Services contracts 
Summer 2026 to summer 2027Construction